Established with a dedicated focus on Construction Management, Construct NV is committed to empowering local government agencies in efficiently executing their projects. With a primary emphasis on construction managers, field inspectors, and document control specialists, Construct NV leverages its profound expertise in urban infrastructure development to ensure successful project delivery.
I-15 South Project: Sloan Road to North of Warm Springs Road
Construction begins January 2024
PROJECT OVERVIEW:
The Nevada Department of Transportation (NDOT) will begin improvements along nearly nine miles of Interstate 15 (I-15) South from Sloan Road to north of Warm Springs Road beginning in January 2024. This Project will aid in improving travel-time reliability, serve proposed growth in the area by increasing local mobility and access, and enhance I-15’s operational efficiency. Construction is anticipated to be completed within a 24-month period.
PROJECT TEAM
Shawn Meagher, PE
PROJECT FEATURES:
• Widening I-15 from six to eight general-purpose lanes between Sloan Road and St. Rose Parkway
• Widening and restriping I-15 from six to 10 general-purpose lanes between St. Rose Parkway and Blue Diamond Road
• Adding a High Occupancy Vehicle (HOV) lane in each direction between St. Rose Parkway and Blue Diamond Road
• Resurfacing bridges and pavement preservation at the Blue Diamond Interchange
• Construction of 10 new sound walls near qualifying residential areas throughout the corridor
PROJECT COST AND FUNDING:
The total cost for construction is $86 M. The project is paid for with 95% federal and 5% state funds. Funding sources include National Highway Performance Program (NHPP), Surface Transportation Block (STBG) and PROTECT Program grants, and state gas tax.
Contractor
Fisher Industries
SCHEDULE:
Below is a general overview of the construction schedule. The schedule is subject to change.
January-June 2024:
• Earthwork and widening SB I-15 from St. Rose Pkwy. to Sloan Rd.
• Earthwork and widening both SB and NB I-15 from St. Rose Pkwy. to Silverado Ranch Blvd.
• Earthwork and widening SB I-15 from St. Rose
• Concrete grinding at the Sloan Rd. interchange
• Drainage and electrical improvements
• Bridge resurfacing at Blue Diamond Rd.
• Begin forming sound walls
July-December 2024:
• Earthwork and widening NB I-15 from Sloan Rd. to St. Rose Pkwy.
• Drainage and electrical improvements
• Forming sound walls
• Installing overhead signs
• Rock landscaping
• Fence and guard rail installation
January-June 2025:
• Earthwork and widening NB I-15 from Cactus Ave. to Silverado Ranch Blvd.
• Earthwork and widening SB Blue Diamond Rd to Silverado Ranch Blvd.
• Drainage and electrical improvements
• Forming sound walls
• Rock landscaping
• Fence and guard rail installation
• Installing overhead signs
July-December 2025:
• Mill and fill existing asphalt NB and SB from Warm Springs Rd. to Sloan Rd.
• Electrical improvements
• Rock landscaping
• Fence and guard rail installation
TRAFFIC CONTROL:
Project working hours are nightly, Sunday nights starting at 8 p.m. through Friday evenings at 5 p.m.
• Drivers can expect lane shifts and lane reductions to occur with a reduced speed of 55 MPH.
• During daytime hours, Monday-Friday from 5 a.m. to 8 p.m., three lanes of traffic will be maintained in each direction.
• Traffic will be reduced to one lane of traffic in each direction nightly, Sunday-Friday 8 p.m. to 5 a.m.
Project Background
In 2008, an Environmental Assessment (EA) was prepared for the I-15 South Corridor Improvement Project, addressing the environmental effects of improvements along the I-15 corridor, including a portion of Las Vegas Boulevard South, between Sloan Road and Tropicana Avenue. A Finding of No Significant Impact (FONSI) for the overall project was approved by the Federal Highway Administration on April 20, 2009.
In 2022, a reevaluation of the I-15 South EA and FONSI was done to consider changing conditions and new issues that have transpired over the last several years within the I-15 South project area. The reevaluation of effects of the Phase 2 improvements was approved by FHWA and the project immediately moved forward into design. Design plans were finalized in the summer of 2023.
I-15 South Corridor Improvement Project EA_2008
I-15 South FONSI – FHWA_2009
Reevaluation_2023
CC-215/US95 INTERCHANGE NDOT 3833 CENTENNIAL BOWL, PHASE 3D
LAS VEGAS, NV
PROJECT VALUE
$500,000,000
PROJECT SCHEDULE
January 2010 – December 2023
PROJECT RELEVANCY
Similar to other staff augmentation of Beltway segments Construct NV provided professional staff for all positions including Assistant Resident Engineer, Schedule Reviewer, and Inspectors. Construction of this project involved 20 bridge structures, concrete roadway (PCCP), drilled shafts, asphalt paving, retaining walls, drainage structures, and traffic signal/ ITS facilities.
PROJECT TEAM
Shawn Meagher, PE
DETAILED DESCRIPTION: Phase 3D is the final phase of the Centennial Bowl which consisted of construction of 16 bridges, three remaining ramps to complete the US 95/CC- 215 interchange; new slip ramps at Oso Blanca, widening of northbound US 95, new sewer line work, and constructing a multi-use path along CC-215 from Gran Montecito Parkway to Tenaya Way.
The overall $500 Million program will finalize the transportation improvement efforts by NDOT in the Northwest region by completing this interchange in Q1 of 2024.
Construct NV augmented NDOT by providing an Assistant Resident Engineer who performed a Constructability Review, Quality Assurance/Quality Control Review, Developed and Updated the Project Schedule, Construction Cost Estimating, Limitations of Operations, and creation of Construction Phasing while also providing technical bridge, road, electrical, drainage, and retaining wall inspections.
Peace Way Bridge
PROJECT TEAM
Mike Mamer, CCM
Project Information
Clark County Public Works (CCPW) is constructing a bridge on Peace Way over the CC 215 West Bruce Woodbury Beltway. The bridge will connect Peace Way between Fort Apache Road to Chessie Court. There will be no access to CC 215 from Peace Way. The project will also include roadway rehabilitation and filling in the gaps of pavement to complete the full-width roadway section between Hualapai and Cimarron. The proposed roadway will have two lanes and a bike lane in each direction with a raised median or two-way left-turn lane. Construction is scheduled to start in the 1st quarter of 2024 with a construction duration of approximately 12 months.
Project Limits
Hualapai Way to Cimarron Road
Funded By
FRI
Design By WSP
Certifications
Certifications
CMAA- Construction Management Association of America
NDEP
ATSSA American Traffic Safety Services Association
ICC
Nevada Board of Professional Engineers
NAQTC
American Concrete Institute
American Public Works Association
Memberships
APWA
American Concrete Institute
ASCE
Contact Us
Shawn Meagher 702.481.2362 / shawn.meagher@contructnv.com
Mike Mamer 702.271.2362 / mike.mamer@constructnv.com